M1/WP 16 - Project web site operational

Start date: 1.1.2003  End date: 31.3.2003 Completed: 100%
Results available:
bulletgeneral public pages
bulletgeneral protected pages
bulletStructures stream pages
bulletSAMARIS document management system

M2/WP 12 - Complete review of repair methods for structures

Start date: 1.1.2003  End date: 30.6.2003 Completed: 100%
Results available: Inception report submitted on July 4th

M4/WP13 - Decisions on properties of concretes to be used in laboratory and field test trials of CI

Start date: 1.1.2003  End date: 30.6.2003 Completed: 100%
Results available: Completed

M5/WP14 - Identification of most important phenomena for defining HPFRCC main test programme

Start date: 1.1.2003  End date: 30.6.2003 Completed: 100%
Results available: Completed

M6/WP12 - Complete critical review of relevant R&D work

Start date: 1.1.2003  End date: 30.9.2003 Completed: 80%
Results available: In progress

M11/ WP 15 - Collection of structural data completed

Start date: 1.4.2003  End date: 20.1.2004 Completed: 100%
Results available: Questionnaire received from subcontractors

M12/WP14 - Selection of materials for main test series of HPFRCC

Start date: 1.10.2003  End date: 31.12.2003 Completed: 100%
Results available:  

M16/WP15 - Collection of traffic data completed

Start date: 1.10.2003  End date: 30.6.2004 Completed: 40%
Results available: Polish experiment completed, WIM data evaluated

M18/WP14 - Choice of on-site applications for pilot tests of HPFRCC

Start date: 1.3.2003  End date: 30.9.2004 Completed: 30%
Results available: